What are some generator considerations for powering transitional power during facility shutdowns, maintenance, turnarounds, or oil and gas operations?

When planning for transitional power during facility shutdowns, turnarounds, or oil and gas operations, core considerations must prioritize accurate load sizing, fuel logistics and storage, equipment classification, and comprehensive safety and cable routing.

 

 

 

 

 

  1. Power and Load Sizing
  • Motor Starting Analysis: Ensure the generator can handle the high inrush currents of large industrial motors and pumps restarting after the outage.
  • The 80% Rule: Operate generators at no more than 80% of their maximum rated capacity to ensure reliability and prevent overloads.
  • Load Banks: Avoid “wet stacking” (unburned fuel accumulation) in diesel engines by ensuring the generators are periodically run with a sufficient load.
  1. Fuel Strategy & Logistics
  • Fuel Purity: For oil and gas operations, diesel fuel can become contaminated with moisture and particulates. Fuel polishing and regular filter replacements are critical. 
  • Continuous Refueling: For extended turnarounds, implement a robust refueling schedule and install auxiliary, double-walled fuel tanks to minimize spill risks and maintain uninterrupted operations. 
  • Alternative Fuels: Where available, natural gas-fired generators can eliminate the need for onsite diesel handling, though they require reliable pipeline infrastructure. 
  1. Environment and Safety Classification
  • Classified Zones: In oil and gas environments, temporary power equipment must be certified for hazardous locations (e.g., Class I, Division 1 or 2) to prevent accidental ignition. 
  • Exhaust & Ventilation: Ensure generators are positioned so that exhaust and emissions are kept clear of building air intakes, enclosed workspaces, and confined spaces. 
  • Grounding & GFCI: Verify proper grounding of the generator frame and implement Ground Fault Circuit Interrupter (GFCI) protection for all temporary lighting and tool circuits.
  1. Layout and Distribution Planning
  • One-Line Diagrams: Before work begins, draw up detailed electrical one-line diagrams to track all circuits, transformers, and panel sizes to safely isolate faults.
  • Mini-Grids: For large facility footprints, distributing power via a decentralized “mini-grid” configuration is generally more efficient than running long, high-voltage cables from a single centralized unit.
  • Cable Protection: Elevated or heavily protected trenching of cables is required in heavy-traffic areas to prevent tripping hazards and equipment damage.
  1. Compliance and Temporary Rentals
  • Rental Support: If using rental fleets, ensure providers can offer rapid response, flexible contracts, and staff training.
  • Code Compliance: All temporary setups must comply with OSHA and the National Electrical Code (NEC) standards.

Question 1: What is the peak starting load (inrush current) vs. running load? 

Answer 1: Large motors and compressors require significantly more power to start up than to run, which directly impacts the required kW and kVA.

Question 2: Are you dealing with continuous or intermittent loads? 

Answer 2: Specifying your motor duty cycles (e.g., S1 for continuous) prevents overloading and engine wet-stacking.

Question 3: What is your required voltage, phase, and frequency? 

Answer 3: Verify if your facility operations run on 480V, 208V, or 120V, and ensure the correct phase configuration.